perm filename CROCK[3,PMP] blob
sn#022510 filedate 1973-02-04 generic text, type T, neo UTF8
SDC:
I learned from Al Blue today that you had not received an expected
letter from John. Subsequent research revealed that John hadn't sent
one and now doesn't want to for awhile. Enclosed are a short form
version and a longer expression of my views. I hope that one of
these will cover your needs.
STANFORD UNIVERSITY
Stanford, California 94305
COMPUTER SCIENCE DEPARTMENT Telephone 415-321-2300
extension 4202
February 2, 1973
Mr. Stephen D. Crocker
R & D Program Manager
Information Processing Techniques
Defense Advanced Research Projects Agency
1700 Wilson Boulevard
Arlington, Virginia 22209
Subject: Decommitment of the Processor Project
Dear Steve:
In accordance with your request, we have suspended plans to fabricate
a high speed processor. On this basis, we will not need $200,000 of
the funds allocated under the current contract (SD-183).
Sincerely,
Lester D. Earnest
Executive Officer
Stanford Artificial Intelligence Laboratory
STANFORD UNIVERSITY
Stanford, California 94305
COMPUTER SCIENCE DEPARTMENT Telephone 415-321-2300
extension 4202
February 2, 1973
Mr. Stephen D. Crocker
R & D Program Manager
Information Processing Techniques
Defense Advanced Research Projects Agency
1700 Wilson Boulevard
Arlington, Virginia 22209
Subject: Decommitment of the Processor Project
References:
1. "Proposal for Development of a High Speed Processor", to
Advanced Research Projects Office from Stanford University,
January 1972.
2. Amendment P00023 of Contract SD-183, between Defense Supply
Service - Washington and Stanford University.
3. L. Earnest (Stanford), "High Speed Processor Fabrication",
letter to E. Stubbs (DSS-W), 12 July 1972.
4. E. Stubbs (DSS-W), "Approval of Acquisition or Fabrication
of Facilities", letter to L. Earnest (Stanford), 11 Sept. 1972.
Dear Steve:
The purpose of this note is to record recent discussions and
decisions regarding our processor development project.
Funds for this project were requested in January 1972 (Reference 1),
and received in July (Reference 2). Specific procurement
Mr. Stephen D. Crocker Page 2
authorization was requested on 12 July (Reference 3) and approval
(Reference 4) was received at our office on 13 December. Although we
had formal authority to proceed, we had requested a design review in
mid-January to insure completeness and adequacy of the detailed
design before certain major procurements were undertaken.
PROJECT REVIEW
Our staff went over the design with you and the review committee on
January 15. The general state of the project at that time was as
follows.
1. All logic drawings complete (214 drawings).
2. 16 of 24 printed circuit cards completely designed.
3. 34 of 44 wirewrap cards completely designed.
4. design automation programs operational (and in use at MIT
and DEC).
5. Prototype printed circuit and wirewrap cards fabricated
and tested.
Our schedule called for two and one-half months more of design
review, paper debugging, and design of the remaining 8 printed
circuit and 10 wirewrap cards. Component procurement was to be
Mr. Stephen D. Crocker Page 3
partly overlapped with this phase and all fabrication was to be
complete by the end of June. Our budget for completing fabrication
was $194,315 for parts and services, and $72,499 for management and
staff salaries, miscellaneous direct costs, and overhead, which
totals to $267K.
Following fabrication, there was to be a debugging period of
uncertain duration, depending on the number and difficulty of
problems encountered. Development of Tenex modifications was to go
on concurrently.
COMMITTEE COMMENTS
You and the committee were apparently convinced of the technical
adequacy of the design as far as you could probe it in the time
available. There was some variance of opinion on the schedule, with
the designer's estimates being (predictably) more optimistic than the
committee's. Even so, there appeared to be a consensus that the
processor could be made fully operational by the end of this year,
barring major catastrophe.
I heard no criticism of the fabrication budget estimates. Additional
costs for debugging and initial exploitation of the processor were
not given and are more difficult to estimate. My estimate is about
$80K. Apparently, yours was higher. We were planning to cover these
expenses under our computer facility budget.
Mr. Stephen D. Crocker Page 4
Overall, John McCarthy and I were pleased with the recent performance
of the design group and with the committee's evaluation of their
work.
DISCUSSION
Subsequent to the project review, you asked us not to build the
processor, citing schedule slippage and a changing technical
environment. Indeed, there has been substantial slippage in the
verbal estimates of the design staff. As you are aware, this kind of
optimism is common among designers, especially young ones.
As far as formal schedule commitments are concerned, we were not so
far off. Our request for approval (Reference 3) estimated completion
by 1 February 1973 contingent upon receipt of approval by 1 August
1972. In fact, approval was received 13 December 1972 and our most
recent estimate for fabrication was about 1 July. I do not wish to
argue that there was a month-for-month slip associated with delay in
approval, but there was some coupling.
Of course, a project should not be halted for delays if it still
makes sense technically and there are adequate funds available.
There were adequate funds available.
The most recent development on the technical front, our spies tell
us, is that DEC is designing a machine that may come within a factor
Mr. Stephen D. Crocker Page 5
of 2 of the performance of the one we have designed and that theirs
will be probably be cheaper than ours would in production. That will
be an interesting machine if it pans out.
Meanwhile, the one that our group has designed is ready to build and
has a much higher performance/cost ratio than anything on the market
or likely to appear in the next two years. Making the pessimistic
assumption that at most one machine would be built, the question to
ask in our current position is "Is it worth $350K (or whatever figure
you believe) to have a processor 4 times as fast as a KI-10 by the
end of this year?" I believe that the answer is yes.
DECISIONS
While not fully understanding your reasons for requesting a halt, we
agreed to suspend procurement on the processor project. You remarked
that you had no objection to our completing design details and trying
to convince you that the processor should be built, but you assigned
low probability to that outcome. Our staff subsequently decided to
proceed on that basis.
You also asked that we inform your office by the next morning of the
amount in the contract that we would not need, given that the
processor will not be built. I subsequently pointed out that our
computer system remains badly overloaded and that we must get more
Mr. Stephen D. Crocker Page 6
performance in some way. I suggested that the available funds might
be diverted to the procurement of a KI-10 processor from DEC, which
would provide some increase in performance and would permit us to
convert to the Tenex monitor. You said that was not possible.
On the basis of these decisions, I reported to Al Blue (ARPA) that we
could leave $200,000 unspent.
CONCLUSIONS
As I write this, it is 2 AM and there are 22 people running on our
system. This is not unusual. Daytime loads almost always exceed 40
jobs. As far as I know, there is no other PDP-10 installation on the
network that regularly carries half this load.
As things stand, we have an overloaded timesharing system, a slightly
disillusioned and very disgruntled design group, and little prospect
for improvement in either. We remain convinced that the new
processor was and is a sound investment and hope to convince you of
this.
Mr. Stephen D. Crocker Page 7
In considering alternatives, I trust that you will remember that
while hardware can never compete in performance with paper machines,
neither can paper machines compete with planned machines. We solicit
your help in finding solutions to our problems.
Sincerely,
Lester D. Earnest
Executive Officer
Stanford Artificial Intelligence Laboratory
cc: L. Roberts, A. Blue (ARPA)